Dealing With Disputes Beneath the Party Wall Etc Act 1996

Dealing With Disputes Beneath the Party Wall Etc Act 1996

When  https://squareblogs.net/fendertile3/finding-a-party-wall-notice  carry out work on structures distributed to or near a neighbour's property, the proper course of action would be to issue a notice under the Party Wall etc Act 1996. But what comes  Party Wall Surveys Upton Park ? This article describes the process that follows the issuance of a notice, explaining how to deal with a dispute to your notice, and what to expect from the Party Wall Award.

What if a Dispute Arises?

Once you have issued a notice under the Party Walls etc Act, if agreement cannot be reached between neighbouring parties or the notice has expired, the problem is in dispute.

The process is as follows:

1. Surveyors are often appointed by each of the Owners. Alternatively, the parties can appoint an 'Agreed Surveyor', who is acceptable to all or any parties.

2. The Agreed Surveyor, or the average person Surveyors jointly, will produce an Award which should be fair and impartial to all or any parties.



3. Where each one of the Owners appoints a surveyor, they jointly decide on a Third Surveyor who when the appointed surveyors cannot acknowledge any point will become an 'umpire'.

The Publication of an 'Award' or 'Party Wall Award'

The Award usually includes the next elements;-

1. The scope of the works proposed by the Building Owner together with any ancillary temporary works and protection to avoid damage.

2. A Schedule of Condition, that is an agreed record between your surveyors of the adjoining properties condition that's likely to be affected by the proposed works.

This Schedule is re-checked upon completion of the works, and any damage noted.

3. A WAY Statement and drawings (architectural/structural engineers) which indicate how the work is to be carried.

4. A list of hours and days of permitted noisy working with regard to the matters awarded - the Award will not control noise, pollution, hours nor days of working in the remainder of the site.

5. The proper for either of the appointed surveyors to possess usage of inspect the works. That is for the surveyor to check on that the works are increasingly being completed as agreed, and allows the surveyor to inspect the neighbouring property for damage or a particular constructional detail.

6. A confirmation of who is in charge of the fees for drawing up the Award and for checking that the work has been carried out in accordance with the award. It really is usual for the Building Owner to pay all costs associated with drawing up the Award if the works are solely for his benefit.

7. A confirmation of who is in charge of payment for the works. This is usually the Building Owner because they are for his benefit. However, you can find cases where in fact the Adjoining Owner may be responsible for paying for the main cost, for example: where work to a celebration wall is needed due to defects that the Adjoining Owner is responsible or where he requests work to be done for his benefit.

8. A requirement that prior to the works going ahead that unconditional planning permission (normally planning permission is granted with conditions and these ought to be extinguished) is set up together with building regulation approval.

9. Provision for the surveyors to make further Awards, for example; where in fact the scope of the works alters due to site conditions or upon the works being exposed.

Following the Publication of the 'Award' or 'Party Wall Award'

After 14 days have elapsed lacking any appeal being made to the County Court by either Owner on the grounds that the Award has been made improperly the Building Owner is at liberty to commence the works.

Upon completion of the works, the surveyors will check the Schedule of Condition and note if any damage has occurred. Any noted damage because of the works becomes the liability of the Building Owner to repair/renew/re-decorate OR instead agree a compensation total be paid to the Adjoining Owner

All work must comply with the Award. The Award should be retained and kept with the deeds for future reference since it will need to be produced with confirmation there are no outstanding matters through the conveyance of either of the properties detailed in the Award.